Your present location:HomeApplication caseFOSS?6+1 > Zhoubei Thermal Power Plant, 4 * 130t/h coal-fired boiler

ESSE revamped the old system of Zhoubei FGD system by utilizing maximum the old facilities and optimizing the system, reduced the space required. The initial investment comparing with old process is lower, and the waste water and solids can be fully recycled. The operating cost is reduced by over 20% as well.

 

Performance before and after revamping

 

Item

Inlet SO2 mg/Nm3

Outlet SO2 mg/Nm3

Inlet NOx mg/Nm3

Outlet NOx mg/Nm3

Inlet particle
mg/Nm3

Inlet particle
mg/Nm3

Index

4600

35

-

-

30

5

Item

 Power Consumption
Kwh

Water Consumption
t/h

De-Sulphur agent(MgO)
t/h

Crystal Powder Productivity
t/h

Unit Running Cost/ton of sintering ore
CNY/t

Annual Running Cost saving/
10000rmb

Index

1462

49

1.7

3.5

1580

1260